PMP?每日一練試題內(nèi)容(2022/9/12)
試題1
某項目受各種因素的影響已停工半年,由于市場環(huán)境變化,該項目已不再具備商業(yè)價值。近期臺風(fēng)導(dǎo)致項目外墻倒塌砸傷行人,需支付巨額賠償。公司派你去處理相關(guān)問題,你應(yīng)該如何行動?()查看答案
試題參考答案:C
試題解析與討論:www.pokkc.com/st/4679012577.html
試題2
由于項目相關(guān)方對項目需求和關(guān)鍵可交付成果的意見不一致,項目經(jīng)理無法獲得項目發(fā)起人的范圍批準(zhǔn),若要獲得范圍批準(zhǔn),項目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:C
試題解析與討論:www.pokkc.com/st/4610523260.html
試題3
A project sponsor decides to add a feature to the project that affects the project cost, schedule,and scope. The change is approved by the change control board. Which process govern s the project manager's implementation of the approved change?()查看答案
試題參考答案:C
試題解析與討論:www.pokkc.com/st/4905126756.html
試題4
一個新項目的項目經(jīng)理獲得四名必要授權(quán)發(fā)起人中三人的簽署同意,第四名項目發(fā)起人將在兩周內(nèi)度假回來。項目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:D
試題解析與討論:www.pokkc.com/st/4692620264.html
試題5
你正在管理來自兩個客戶的兩個不同項目。在和一名客戶會面的時候,你發(fā)現(xiàn)有一條敏感信息,可以幫助另外一名客戶節(jié)約大筆的項目預(yù)算。請問你應(yīng)該怎么做?查看答案
試題參考答案:B
試題解析與討論:www.pokkc.com/st/4731229279.html
試題6
問題日志的用于∶查看答案
試題參考答案:B
試題解析與討論:www.pokkc.com/st/4926711109.html
試題7
A project manager is developing the stakeholder engagement plan and identifying a stakeholder with a high level of power but low level of interest in the project. How should the project manager deal with this stakeholder?查看答案
試題參考答案:D
試題解析與討論:www.pokkc.com/st/4791517031.html
試題8
項目團隊和第三方供應(yīng)商簽訂合同,要求開發(fā)指定的設(shè)備。第三方供應(yīng)商不希望接受項目期間成本增加的風(fēng)險,而項目團隊希望盡量降低設(shè)備質(zhì)量差的風(fēng)險。什么樣的合同類型對項目團隊和第三方供應(yīng)商最有利?查看答案
試題參考答案:A
試題解析與討論:www.pokkc.com/st/4886922410.html
試題9
To generate creative ideas during the Collect Requirements Process, the project manager solicits a group of experts through a series of questionnares,and whose answers are went directly back to the project manager. This technique is as know n as which of the following?查看答案
試題參考答案:A
試題解析與討論:www.pokkc.com/st/481464953.html
試題10
由于不斷變化的立法項目團隊識別到大量額外的需求.項目經(jīng)理要求團隊針對每個需求提交變更請求,項目經(jīng)理下一步應(yīng)該怎么做?查看答案
試題參考答案:B
試題解析與討論:www.pokkc.com/st/460914978.html
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |