試題題型【單選題】
試題內(nèi)容

Every documented change request needs to be either approved or rejected by a responsible individual sually( ).
A. the project sponsor
B. an individual
C. any stakeholeder
D. quality controller

查看答案

相關(guān)試題

67題: The information is circulated through communication processes.( )is not included in Work Performance Information.
A. The status of deliverables
B. Implementation status for change requests
C. Forecasted estimates to complete
D. Work performance report
答案解析與討論:www.pokkc.com/st/3976411359.html

68題: ( )is not included in Information Security Risk Assessment Process.
A. Establishing information security risk criteria
B. Identifying the information security risks
C. Formulating an information security risk treatment plan
D. Analysing the information security risk
答案解析與討論:www.pokkc.com/st/3976520693.html

69題: ( ) is not included in Perform Integrated Change Control Process.
A. Defining subsidiary plans
B. Approving changes
C. Managing changes to deliverables
D. Reviewing all change requests
答案解析與討論:www.pokkc.com/st/3976618660.html

71題: ( )in not included in Control Quality input documents.
A. Project management plan
B. Project documents
C. Quality problems report
D. Work performance data
答案解析與討論:www.pokkc.com/st/39768945.html